What to do when a client moves the deadline mid-project

Before saying yes to a moved launch: re-plan backwards, date the client's own inputs, offer a choice if it will not fit, and update every date once.

· 5 min read · Client delivery

When a client moves a deadline mid-project, re-plan backwards from the new date before you agree to it. Work out what the client must supply and approve by when, and if the plan no longer fits, put a choice in front of them. Then update every affected date in one place, with the reason, on the same day.

Moving dates are normal. PMI's 2018 Pulse of the Profession found that 52% of projects completed in the previous year had experienced scope creep or uncontrolled change, up from 43% five years earlier (PMI, 2018). That survey covers projects of every kind and is several years old, but no agency would guess lower today. The change itself rarely does the damage. The damage comes from agreeing to it on a call and working out what it means afterwards.

This guide is about the client's date moving. When your own delivery date slips, the case for showing the new date and the reason is made in landing dates, not deadlines.

First, find out what actually moved

"The launch has moved" can mean four different things, and each needs a different response:

Ask in so many words: "Is the 30th now fixed, and is the list of deliverables still the same?" It is a short question, and it can save a week.

Re-plan backwards from the new date

Start at the launch and walk back. For every deliverable still open, the plan needs:

  1. The date it must be approved by to make the launch.
  2. The review window before that date, which is client time.
  3. The date the studio has to send it for review.
  4. Anything the client owes before work can start: copy, assets, access, a decision.

The review windows are where compressed plans break. A studio can add evenings. A client's marketing director cannot review two rounds of the homepage in one afternoon while also signing off the brochure. If the new plan needs reviews to happen faster than this client has ever managed, it will fail, and you will be the one explaining why.

Put the client's dates in the plan

Most re-plans list the agency's dates and leave the client's commitments implied. That is how a compressed timeline dies in week two: the photography arrives four days late, and on paper the launch has not moved at all.

Write the client's inputs down as dated items, each with a named owner on their side. Final copy from Sarah by Tuesday. Product photography by Friday. Homepage approval by the 18th. Those dates decide the launch as much as anything the studio does, and seeing them in writing is often the moment a client realises the new date was optimistic.

When it does not fit, offer a choice

Sometimes the maths works. When it does not, resist absorbing the gap quietly with late nights. Put the options in front of the client with what each one costs:

Let the client choose. A plan the client picked is one they will defend to their own boss. A plan handed to them is one they will resent the first time it bites.

Tell everyone once, in writing

After the call, send one message that stands on its own: the new date, what moved and what stayed, what the client owes and by when, and which option they chose. Then update every affected date where both sides can see it, each carrying the reason, for example "launch brought forward to the 30th at the client's request".

Two details make this work. Say who asked for the change, plainly and without edge, because six weeks later nobody will remember. And if the change costs money, say so in the same message. Raised at the moment of change, extra cost is a line on a quote. Raised at the invoice, it becomes an argument.

The trap when the date moves later

A later deadline feels like good news, and for about a week it is. Then the work spreads to fill the new time, the team gets pulled onto a louder client, and the new date arrives with the scramble the old one would have had.

Keep the studio's internal milestones close to where they were, and spend the slack on purpose: an extra review round, the phase-two work, or someone else's launch. Also ask why the date moved. A launch pushed back because the board has not agreed the positioning will very likely come back with new copy attached.

Questions agencies ask about moving deadlines

Should we charge when a client brings a deadline forward?

If it needs overtime, extra people or rushed third-party costs, yes, and say so before starting. If it only reorders work the team was doing anyway, charging usually costs more goodwill than it earns.

How do we tell a client their new deadline is unrealistic?

Show them the plan worked backwards, with their review windows and their inputs in it. People accept a calendar far more readily than an opinion. Then offer the options, so the conversation moves straight to what they are willing to give up.

What if the deadline keeps moving?

Treat a third move as information about the client's own decision-making. Agree a date after which the launch is fixed, and a price for moving it again, and put both in writing.

Where HoopoeHQ fits

In HoopoeHQ a campaign carries its start, launch and end dates on the workspace timeline, and every request filed under it sits beneath the bar. When the launch moves, any open request now landing after it is flagged as at risk, so the re-plan starts from a list instead of a hunch. Landing dates move with a reason both sides can see, and the client's portal shows them the same timeline. There is more on the campaign timeline.